Project: Brooklyn Bridge  Grid Manufacturer: LB Foster 

Location: NYC, NY  Contractor: Yonkers(main span) - Skanska(approach spans)

Install Date: 2000 main span - 2010 approach spans  Design Engineering Company: WEI  Bridge Owner: NYCDOT

 

Project Description: Main span redecked in 1999 using 130 nights of construction (11PM - 6AM ) keeping bridge fully open at all other times.  Approachs were redecked in 2010 using similar techniques with steel grid bridge deck panels precast with concrete to speed construction.